Iron ore extracted from Sangan iron ore mines after being transported to the mouth of the crusher, by a The gyratory stone crusher with a capacity of 2500 tons per hour is crushed up to 200 mm in size and by
The apron feeder machine with a yield capacity of 1800 tons per hour is loaded on the conveyor belt.
The stone transfer line with a length of approximately 4.7 km, transported the crushed iron ore from the crusher to the vicinity of Opal Parsian Sangan concentrate factories and finally by a conveyor to
The length is 600 meters and the stacker is stored in the stockpile area.
The crusher unit, transfer line and stone depot are responsible for supplying 10 million tons of feed to the concentrate factories of Opal Parsian complex.